Proceeding Of Petition No :- 28/2020
Sno Hearing Date Procceding
1 10-03-2021 Order Passed on
10-03-2021
2 03-03-2021 Hearing held through video conferencing.

Shri Raunak Jain, Counsel alongwith Shri Vinay Agrawal and Shri Sudeep Chakraborty (present in courtroom) for the petitioner.

Shri Abhinav Kardekar and Ms. Gurpreet Kaur Chawla, Counsels along with Shri Robin Gupta, EE for respondent.

2. Heard the parties.

3. The case is reserved for order.
3 01-03-2021 Hearing held through video conferencing.

Raunak Jain, Counsel, Shri Arun Poddar and Shri Sudeep Chakraborty (Physically Present) for the petitioner.

Ms. Gurpreet Kaur Chawla, Counsel along with Shri Robin Gupta, EE (Physically Present) for respondent.

2. Shri Robin Gupta submitted letter no. 2740 dated 01.03.2021, vide which those terms and conditions are communicated, on which both the parties agreed, if the petitioner replaces it’s existing captive power plant by a solar power plant.

3. The Commission feels that study of the proposal is required keeping in view the provisions of the RE Regulations.

4. With consent of the parties, the case be listed for hearing on 03.03.2021 at 3:00 PM.
4 12-02-2021 Hearing held through video conferencing.

Raunak Jain, Counsel and Shri Sudeep Chakraborty for the petitioner.

Ms. Gurpreet Kaur Chawla, Counsels along with Shri Robin Gupta, EE for respondent.

2. The petitioner informed that as per advice of the Commission, several meetings held between the parties and a fruitful outcome is expected soon for which he sought time. Considered the request and allowed two weeks time.

3. The case is fixed for hearing on 01.03.2021 at 3:00 PM.
5 18-01-2021 Hearing held through video conferencing.

Raunak Jain, Counsel and Shri Sudeep Chakraborty for the petitioner.

Shri Abhinav Kardekar and Ms. Gurpreet Kaur Chawla, Counsels along with Shri Robin Gupta, EE for respondent.

2. The petitioner informed that as advised by the Commission in hearing held on 02.12.2020, meetings held between the parties, but no consensus could be reached. He seeks three weeks time for resolving the issues mutually. Considered the request and allowed three weeks time.

3. The case is fixed for hearing on 12.02.2021 at 11:30 AM.
6 22-12-2020 Shri Sudeep Chakraborty and Shri Arun Poddar present in the courtroom for the petitioner.

Shri Abhinav Kardekar and Ms. Gurpreet Kaur Chawla, Counsels along with Shri Robin Gupta, EE for respondent through video-conferencing.

2. The petitioner submits that the meeting with CSPDCL to resolve the issues could not be held due to unavoidable reasons. Hence, seeks time for resolving the issues. Considered the request and allowed two weeks time.

3. The case is fixed for hearing on 18.01.2021 at 3:30 PM.
7 02-12-2020 Shri Raunak Jain, counsel joined through video conferencing, Shri Vinay Agrawal and Shri Sudeep Chakraborty present in the court room for the petitioner.
Ms. Gurpreet Kaur Chawla, Counsel along with Shri Robin Gupta, EE for respondent through video-conferencing.
2. During the course of hearing, Ms Chawla requested that issues of this case are similar to Suo-Motu petition No. 61 of 2020 and, therefore, the case be heard with the petition No. 61 of 2020.
3. The petitioenr submits that their case is different as it relates to substitution of conventional plant by the solar plant.
4. Considering the submission of the petitioner, we direct him to give their proposal within a week and provide copy to the respondent. The respondent may make submission on the proposal at least a day before the next date of hearing.
5. If the parties think appropriate, they can meet together and discuss the proposal to arrive at an amicable solution.
6. The case is fixed for discussion on proposal on 22.12.2020 at 3:30 PM.
8 07-10-2020 The case was listed for hearing on 03.09.2020. Due to detection of Covid-19 cases in the office of the Commission, office was closed and, therefore, the case was adjourned.

3. The case be listed for hearing on 02.12.2020 at 03:30 PM.
9 13-08-2020 The case was listed for 05.08.2020. Due to COVID-19 lockdown declared by the State Govt., hearing could not be held on the scheduled date.

2. The case be listed for hearing on 03.09.2020 at 3:30 PM.
10 10-07-2020 Shri Raunak Jain, counsel joined through video conferencing, Shri Vinay Agrawal and Shri Arun Poddar present in the court room for the petitioner.
Shri Abhinav Kardekar and Ms. Gurpreet Kaur Chowla, Counsels along with Shri Robin Gupta, EE for respondent through video-conferencing.
2. During the course of arguments, the Commission raised certain queries relating to relaxations sought in the regulation. The counsels sought time. Prayer allowed.
3. The case is fixed for final hearing on 5th August 2020 at 3:30 PM.
11 26-06-2020 Shri Arun Poddar for petitioner.
Shri Abhinav Kardekar, Counsel for respondent through video-conferencing.
2. The respondent counsel submits that the rejoinder is received by them day before yesterday only and, therefore, request for time to study the same. We accept his prayer.
3. Consent of the parties, the case is listed for final hearing on 10.07.2020 at 3:30 PM.
12 06-06-2020
13 06-06-2020 Commission Order for Hearing on 26.06.2020 at 12:00 PM
14 19-03-2020 Shri Arun Poddar for petitioner.
Ms. Gurpreet Kaur Chawla, Counsel along with Shri Robin Gupta, EE for respondent.

2. The respondent’s counsel Shri Abhinav Kardekar filed an application on 17.03.2020 for adjournment on account of notification dated 16.03.2020 issued by the Hon’ble High Court of Chhattisgarh regarding fight against Corona Virus. It is intimated by petitioner also that due to precautionary advice given by the Central Government against the global pandemic Corona Virus, the counsel for petitioner Shri Raunak Jain who comes from Delhi, is unable attend hearing today and seeks postponement.

3. Considered the request and accepted them.

4. The petitioner seeks time for filing of rejoinder. The petitioner is allowed three weeks time for filing of rejoinder with copy to the respondent.

5. The case be listed for hearing on 02.05.2020 at 12:00 noon.
15 13-02-2020 Shri Raunak Jain, Counsel for petitioner.

Ms. Gurpreet Kaur Chawla, Counsel along with Shri Robin Gupta, EE for respondent.

2. The respondent counsel seeks two week’s time for filing reply. Time granted.

3. The respondent is directed to submit reply with affidavit by 03.03.2020 with copy to the petitioner. The petitioner may file rejoinder, if any, by 12.03.2020 with copy to the respondent. The parties must adhere to the prescribed time limit.

4. The case be listed for hearing on 19.03.2020 at 12:00 noon.