Orders passed in petition

  Court Proceeding of petition No. 11/2017 (M)

S.No. Hearing Date Procceding
1 2017-07-20 Shri M.N. Biswas, present for respondent M/s ACB (India) Ltd. No one present for Chief Electrical Inspector (CEI) and Chhattisgarh State Power Distribution Company Limited (CSPDCL).

2. Despite service of notice, no one present for respondent CEI and CSPDCL. Both the offices be issued show cause notice to clarify why action should not be taken against them for non-compliance of Commission's notice.

3. The respondent admits the data submitted by the Chief Electrical Inspector. The respondent further submits that cross subsidy is being paid by them according to the Regulations.

4. The CSPDCL shall be asked to verify the statement of the respondent whether cross subsidy is being paid or not.

5. The case is closed for orders.
Status: Close for Order

2 2017-06-07 Commission order for hearing
Status: Processing