S. No
|
Petition No.
|
Parties
|
Subject
matter of the Petition
|
Date of Filing
|
Date of Disposal/ Order
|
Remarks
|
|
1.
|
01/09(M)
|
Suo
Motu
CSPDCL
Respondent
|
U/s
142 of the Electricity Act for Non-compliance of
order dated 26-04-2008 of Electricity Consumers Grievances
Redressal forum. (M)
|
14.01.2009
|
Order Passed on 19.03.2009
|
|
|
2.
|
02/09(M)
|
M/s
Arasmeta Captive Power Company Ltd. V/s CSPDCL
|
Reduction
in Existing Contract demand up to zero. (M)
|
20.01.2009
|
Order Passed on 05.06.2009
|
|
|
3.
|
03/09(OA)
|
M/s
Arasmeta Captive Power Company Ltd. V/s SLDC
and others
|
Short
term Inter State Open Access for sale of power to
PTC or any such trader.(OA)
|
10.02.2009
|
The petitioner does not want
to press the petition. The petition is accordingly
dismissed
|
|
|
4.
|
04/09(M)
|
M/s
R.R. Eneryg Ltd. V/s CSPDCL
|
Permission
for reduction of contract demand. (M)
|
09.02.2009
|
Closed
on 23.04.2009
|
|
|
5.
|
05/09(M)
|
M/s
Monnet Ispat & Energy Ltd. V/s CSPDCL
|
Petition
for quash panel UI demand charges. Charged by
respondent. (D)
|
09.02.2009
|
Order Passed on 24.10.2009
|
|
|
6.
|
06/09(M)
|
M/s
Sai Chamicals Pvt. Ltd. V/s 1.
CSPDCL 2.
CSPTCL
|
To
allow provisional open access under present
connectivity condition and to provide independent
connectivity to Bio Mass based power plant. (M)
|
11.02.2009
|
Order Passed on 29.06.2009
|
|
|
7.
|
07/09(M)
|
Suo
Motu
Executive
Engineer city Division (East)-I
CSPDCL....
Respondent
|
U/s
142 of the Electricity Act. for Non-Compliance of
order dtd. 30.06.08 of Electricty Consumer Grievances
Redressal Forum. (M)
|
18.02.2009
|
Order Passed on 31.03.2009
|
|
|
8.
|
08/09(M)
|
Suo
Motu
Executive
Engineer (O&M
CSPDCL...
Respondent
|
U/s
142 of the Electricity Act. for Non-Compliance of
order dtd. 14.11.08 of Electricty Consumer Grievances
Redressal Forum.(M)
|
18.02.2009
|
Order Passed on 29.05.2009
|
|
|
9.
|
09/2009(T)
|
Suo
motu
|
Discussion
paper on "pricing of surplus power from
captive generating plants & IPPS for the year
2009-10 for short -term purchase by distribution
utility state.
|
18.02.2009
|
Order Passed on 18.04.2009
|
|
|
10.
|
10/2009(T)
|
Chhattisgarh
State Power Generation Company Ltd. and others
|
Petition
for Aggregate Revenue Requirement for F.Y. 2008-09
and 2009-10 and Tariff Petition for F.Y.
2009-10 filed by Chhattisgarh State Power
Generation Company Ltd.. (T)
|
25.02.2009
|
Order Passed on 30.05.2009
|
|
|
11.
|
11/2009(T)
|
Chhattisgarh
State Power Transmission Company Ltd.
|
Petition
for Aggregate Revenue Requirement for FY 2008-09
& 2009-10 and Tariff Petition for F.Y.2009-10
filed by Chhattisgarh
State Power Transmission Company Ltd.
(T)
|
25.02.2009
|
Order Passed on 30.05.2009
|
|
|
12.
|
12/2009(T)
|
Chhattisgarh State
Power Distribution Company Ltd.
|
Petition
for Aggregate Revenue Requirement for FY 2008-09
& 2009-10 and Tariff Petition for F.Y.2009-10
filed by Chhattisgarh
State Power Distribution Company Ltd. (T)
|
25.02.2009
|
Order Passed on 30.05.2009
|
|
|
13.
|
13/2009(M)
|
M/s
Arasmeta Captive Power Company Ltd. V/s CSPTCL
|
Petition
for extension of period completing the independent
lines and relaxation in provision of applicability
Clause of 4.12 Chhattisgarh Electricity Grid Code
and Short Term Open Access. (M)
|
27.02.2009
|
Order Passed on 18.06.2009
|
|
|
14.
|
14/2009(M)
|
M/s
Lahari Power & Steel Lltd.
V/s
Chhattisgarh State
Power Distribution Company Ltd.
Chhattisgarh
State Renewable Energy Development Agency, Raipur
|
To
exit from Power Purchase agreement for Biomass to
converted as independent power plant primarily
using Biomass/Coal. (M)
|
11.02.2009
|
Rejected
at the stage of admission on 09.04.2009
|
|
|
15.
|
15/2009
|
1.
CSPGCL
2.
CSPDCL
3.
CSPTCL
|
Business
plan of CSPGCL, CSPDCL & CSPTCL for control
period from FY 2009-10 to FY 2011-12.
|
03.03.2009
|
Order Passed on 19.06.2009
|
|
|
16.
|
16/2009(M)
|
M/s.
Aryan Coal Benefications Pvt. Ltd.
V/s.
CSPDCL
|
To
review order dated 23.01.09 passed in petition No.
10, 11/2008(M)
|
09.03.2009
|
Rejected
on 25.05.2009
|
|
|
17.
|
17/2009(T)
|
M/s.
Jindal Steel and Power Ltd.
Download
|
Annual
Revenue Requirement for the distribution business
of the petitioner company for F.Y. 2009-10.
|
27.02.2009
|
Order Passed on 27.06.2009
|
|
|
18.
|
18/2009(M)
|
M/s.
CSPDCL
V/s.
M/s.
Jindal Power Ltd.
|
Approval
of draft agreement to be executed between M/s.
Jindal Power Ltd. & Chhattisgarh State Power
Distribution Co. Ltd. for supply of 150 MW power
by Jindal Power Ltd.
|
26.03.2009
|
Order Passed on 13.04.2009
|
|
|
19.
|
19/2009(M)
|
M/s.
CSPDCL
V/s.
M/s.
Jindal Power Ltd.
|
Purchase
of power by Chhattisgarh State Power Distribution
Co. Ltd. from M/s. Jindal Power Ltd. through 400
KV route for approval of supplementary PPA
|
|
Order Passed on 04.04.2009
|
|
|
20.
|
20/2009(M)
|
M/s.
CSPDCL
|
Petition
to review order dated 31.12.2008 passed in P.No.
39/2006 U/R 43(1) of the CSERC (Conduct of
Business) Regulations, 2004
|
26.03.2009
|
Order Passed on
13.10.2009
|
|
|
21.
|
21/2009(M)
|
Suo
Motu
1.
CSPDCL.& 20 Others.
Respondent
|
|
13.04.2009
|
Order Passed on
05.12.2011
|
|
|
22.
|
22/2009(M)
|
M/s KVK Bio-Energy Pvt.Ltd.
V/s
1. CSPDCL
2. SLDC. Bhilai
3. Chhattisgarh State
Renewable Energy Development Agency.
|
Petition for termination of
PPA with the CSEB & grant of interstate short
term open access.
|
09.04.2009
|
Order Passed on
18.05.2010
|
|
|
23.
|
23/2009(M)
|
Chhattisgarh Biomass Energy
Developers Association.
V/s
CSPDCL. Raipur
|
Application U/s 142 of the
Electricity Act 2003.
|
13.04.2009
|
Order Passed on 18.06.2009
|
|
|
24.
|
24/2009(M)
|
Suo Motu
1. Chief Engineer (O
&M)
2. Chief Engineer
(S&P) Respondent
|
Non Compliance of the
provisions of the Electricity Act 2003 & Order
of directions of the Commission in respect of cent
percent meterization.
|
15.04.2009
|
Order Passed on 08.07.2009
|
|
|
25.
|
25/2009(T)
|
Chhattisgarh Biomass Energy
Developers Association
Download
Petition
|
Revision & Determination of tariff for the
purchase of electricity generated by Biomass power
plant in Chhattisgarh by the Distribution
Licensees in Chhattisgarh with effect from
01.04.2009 (Financial year 2009-10 &
subsequent year.
|
28.04.2009
|
Order Passed on
15.04.2010
|
|
|
26.
|
26/2009(OA)
|
M/s. Ind Synergy Ltd.
V/s.
CSPTCL
|
Concurrence for short term
open access for inter-state power sale upto 15MVA
through existing 33 KV dedicated lines.
|
13.05.2009
|
Rejected
at the stage of admission on 06.06.2009
|
|
|
27.
|
27/2009(M)
|
Suo-Motu
CSPDCL Respondent
|
Violation of section 43 of
the Act and the relevant provisions of supply code
|
20.05.2009
|
Order Passed on 25.07.2009
|
|
|
28.
|
28/2009(M)
|
CSPDCL
|
Pricing
of power rquired to be purchased in short term
from CPP & IPP for the year 2009-10
|
25.05.2009
|
Order Passed on 23.06.2009
|
|
|
29.
|
29/2009(T)
|
BSP,
Bhilai
|
Determination
of ARR and tariff for the FY 2009-10 for BSP (T)
|
27.05.2009
|
Order Passed on 31.08.2009
|
|
|
30.
|
30/2009(M)
|
BSP,
Bhilai
|
Approval
of power supply arrangement and business plan for
the Fy 2009-10 BSP.
|
27.05.2009
|
Order Passed on 31.08.2009
|
|
|
31.
|
31/2009(OA)
|
M/s
Vandana Vidyut Ltd. Raipur
Vs
CSPDCL
|
Issue
of concurrence for short term open access for
inter state power sale.
|
28.05.2009
|
Order Passed on 25.11.2009
|
|
|
32.
|
32/2009(D)
|
M/s
Arasmeta Captive power Comp Ltd.
Vs
CSPDCL
|
|
29.05.2009
|
Order Passed on 13.04.2010
|
|
|
33
|
33/2009(M)
|
Suo
Motu
1.
EE, Raigarh
2.
AE (DC), Raigarh
Respondent
|
Under
section 142(2) Electricity Act, 2003 for violation
of the provision of section 43 of the Act of
supply code & for non compliance of
order of forum.
|
27.05.2009
|
Order Passed on 29.06.2009
|
|
|
34
|
34/2009(M)
|
Suo
Motu
CSPDCL ....
Respondent
|
Power procurement plan of
the CSPDCL for year 2009-10
|
09.06.2009
|
Order Passed on 29.06.2009
|
|
|
35
|
35/2009(M)
|
M/s
Ind Synergy Ltd.
V/s
CSPTCL,
CSPDCL & State Load Despatch Centre
|
Issue of concurrence for
short term open access for inter state power sale.
|
09.06.2009
|
Order Passed on 29.06.2009
|
|
|
36
|
36/2009(M)
|
Suo
Motu
State Load Despatch
Centre ....
Respondent
|
U/S 142, of the Act, for
non-compliance of order of the Commission
|
25.06.2009
|
case
closed on 20.07.2009
|
The respondent is directed
to be attentive to the orders being issued by the
Commission
|
|
37
|
37/2009(M)
|
M/s Jayaswal NECO Industries
Ltd. Raipur
|
To review order dated
25.05.2009 passed in suo-motu petition no.
17/2008(M)
|
23.06.2009
|
Order Passed on 05.12.2009
|
|
|
38
|
38/2009(M)
|
BSP
V/s
CSPDCL
|
Petition U/S 42 & 64 of
the Electricity Act 2003, for granting the
categorization of the petitioner as a composite
consumer for additional charge (M)
|
24.06.2009
|
Order Passed on 30.09.2009
|
|
|
39
|
39/2009(M)
|
M/s Corporate Ispat Alloys
ltd.
|
Review of order dated
25.05.2009 passed in suo-motu petition No. 17 of
2008 (M)
|
25.06.2009
|
Withdrawn
by the petitioner
|
|
|
40
|
40/2009(M)
|
M/s
Sharda Energy and Minerals Ltd. & 15
others
V/s
CSPTCL
& SLDC
|
Petition U/s 86(1) (f) of
the Electricity Act, 2003 to quash the penal UI
charges and for remaining of capping of UI charges
on over injection.
|
27.06.2009
|
Order Passed on 24.10.2009
|
|
|
41.
|
41/2009(M)
|
M/s.
Sarda Energy and Minerals Ltd. Raipur
V/s.
CSPDCL
|
Petition
Under Section 86(1)(f) of the Electricity Act,
2003 to issue directives to respondent for correct
calculation of Load Factor as provided in PPA
|
25.06.2009
|
Order Passed on 21.01.2010
|
|
|
42.
|
42/2009(D)
|
M/s.
Bharat Aluminium Company Ltd.
V/s.
1.
Chhattisgarh State Load Despatch Centre, Bhilai
2
Administration CSEB(Re- organization) through
A.C.E. & Nodal Officer STOA
3.
CSPTCL
4.
CSPDCL
|
Petition
against recovery of penal UI charges and wrongly withheld
an amount receivable by the petitioner
|
28.07.2009
|
Order Passed on 24.10.2009
|
|
|
43.
|
43/2009(M)
|
Suo
Motu
1.
M/s. Vandana Vidyut Global Limited., Raipur
2.
M/s. Nakoda Ispat Ltd. Raipur
3.
M/s. Real Ispat & Power Ltd. Borjhara, Raipur
4.
M/s. Singhal Interprieses, Raigarh
5.
M/s. G.R. Sponge & power Pvt. Ltd. Raipur
6.
M/s. API Powertech Pvt. Ltd. Raipur
7.
M/s. Rashmi Sponge Iron & Power Industries
Raipur
8.
M/s. Monnet Ispat & Energy Raigarh
9.
M/s. Corporate ispat Alloys.
Raipur
Respondent
|
U/s.
142 of the Electricity Act.
|
28.07.2009
|
|
|
|
44.
|
44/2009(M)
|
M/s.
Alok Ferro Alloys. Ltd.
V/s.
Chhattisgarh
State power Distribution Company Limited
|
Reduction
in contract demand up to zero
|
25.07.2009
|
Order Passed on 17.12.2009
|
|
|
45.
|
45/2009(M)
|
CSPDCL
v/s.
M/s.
Arasmeta Captive power Company Pvt. Ltd.
|
Review
petition against order dated 05.06.2009 passed in
petition No. 02/2009(M) U/s. 94(1)(f) read with
section 43 of CSERC (Conduct of Business)
Regulation, 2004
|
07.08.2009
|
Rejected
at the stage of admission on 07.09.2009
|
|
|
46.
|
46/2009(D)
|
M/s.
R.R. Energy Lgtd., Raigarh
V/s.
CSPTCL
|
Refund
of 15% supervision charges levied by the
respondent.
|
23.06.2009
|
Order Passed on 29.10.2009
|
|
|
47.
|
47/2009(D)
|
CSPDCL
V/s.
BALCO
|
Petition
filed by CSPDCL to review order dated 27.06.09
passed in petition No. 29/2008
|
04.09.2009
|
Order Passed on 28.10.2009
|
|
|
48.
|
48/2009
|
BALCO
V/s.
CSPDCL
|
Petition
U/s. 142 read section 149 of the electricity Act
2003 filed by BALCO
|
04.09.2009
|
Order Passed on 28.10.2009
|
|
|
49.
|
49/2009(D)
|
M/s.
Lanco Amarkantak Power pvt. Ltd., Korba
V/s.
CSPHCL
|
Petition
against supplementary bill with retrospective
effect raised by the respondent without any
authority
|
11.09.2009
|
Order Passed on 30.03.2010
|
|
|
50
|
50/2009
|
Suo
Motu
CSPHCL
...
Respondent
|
U/s.
142 of Electricity Act 2003
|
16.09.2009
|
Order Passed on 31.10.2009
|
|
|
51
|
51/2009(M)
|
Suo
Motu
The
Superintentding Engineer (City), CSPDCL, Raipur ..
Respondent
|
Non-compliance
of order of the electricity Consumer Grievances
Redressal Forum, Raipur action U/s. 142 of the
Electricity Act 2003.
|
16.09.2009
|
Order Passed on 14.01.2010
|
|
|
52.
|
52/2009(M)
|
Suo
Motu
Chief
Engineer (O&M)
Chief
Engineer (S&P)
Superintending
Engineer (O&M)
All
above are the responsible officers of CSPDCL
|
Non-compliance
of directive in respect of cent percent
meterization. Violation of the Electricity Act
2003, proceeding U/s 142 of electricity Act.
|
22.10.2009
|
Order Passed on 22.07.2010
|
|
|
53.
|
53/2009(M)
|
Suo
Motu
CSPDCL
|
Non
compliance of order dated 05.06.2009 passed in
petition 02/2009
|
13.11.2009
|
Case is closed on 05.12.2009
|
|
|
54.
|
54/2009(M)
|
CSPDCL
V/s.
All
the generators and consumers to whom the peak load
hours are applicable
|
Review
of order dated 25.05.2009 under Suo Motu petition
No. 17/2008(M)
|
30.10.2009
|
Order Passed on 26.12.2009
|
|
|
55.
|
55/2009(M)
|
M/s.
Gayatri Rice Product
V/s.
Chief
Engineer and Others
|
Petition
to quash the bills raised under HT agreement for
consumption of electricity
|
30.10.2009
|
Order Passed on 26.12.2009
|
|
|
56.
|
56/2009(D)
|
M/s.
Gopal Sponge and Power (O) Ltd., Raipur
V/s.
CSPDCL
|
Grant
of permission for synchronization with 33 KV
system of CSPDCL at 220/132/33 KV siltara sub
station and sale of surplus power
|
11.11.2009
|
Order Passed on 29.05.2010
|
|
|
57.
|
57/2009(M)
|
CSPDCL
V/s
Chhattisgarh
Bio-mass Energy Developers association
|
Review
of order dtd 17/09/09 passed in petition no. 25/09
|
30.11.2009
|
Order Passed on 24.04.2010
|
|
|
58.
|
58/2009(M)
|
Sou Motu
The Executive Engineer
(O&M), Division -I Bilaspur
|
Non-compliance of a order of
the electricity consumer givances redressal forum
Bilaspur u/s 142 of the Electricity Act 2003.
|
09.12.2009
|
Order Passed on 14.01.2010
|
|
|
59.
|
59/2009(M)
|
South
East Central Railway
V/s
CSPDCL
|
Petition
against standby feeder maintenance charges levied
by the respondent CSPDCL
|
11.12.2009
|
Order Passed on 28.01.2010
|
|
|
60.
|
60/2009(M)
|
South
East Central Railway
V/s
CSPDCL
|
Petition for adoption of
simultaneous maximum demand for billing of demand
|
11.12.2009
|
Order Passed on 11.03.2010
|
|
|
61.
|
61/2009(M)
|
M/s
Jayaswal NECO Industries Ltd.
V/s
CSPTCL
|
Request
for relaxation of time limit upto 31.12.2011 to
avail the independent connectivity according to
the provision of the CG State Electricity Grid
Code 2007
|
04.12.2009
|
|
|